Monitoring project acceptance key points and completion data list

Release time:2026-05-23 00:00 Views:447 author:Xinlaida Security Technology Department source:technical knowledge
Provide a systematic acceptance check list and a list of materials that should be transferred to avoid disputes due to missing data after delivery.

Acceptance Checklist

Equipment installation

  • The number and location of points are consistent with the design plan (check point by point).
  • The installation is firm, the brackets and poles do not shake; the outdoor equipment is waterproofed in place.
  • The lens is clean, the picture is unobstructed, and the angle meets the design requirements.
  • Cables are clearly marked, strong and weak currents are separated, and wiring is standardized.
  • Grounding and lightning protection meet the requirements and have test records.

Image quality

  • The resolution and frame rate reach the design values.
  • Key areas (faces, license plates, cash registers) can be clearly identified, and screenshots can be saved.
  • Check backlight and night scenes separately to confirm the wide dynamic/night vision effect.
  • No horizontal stripe interference, color cast, blur and other problems.

System functions

  • Real-time preview, multi-screen, and patrol are normal.
  • The recording plan covers the whole day, and playback and retrieval are convenient.
  • The storage capacity meets the storage days requirements and has a margin.
  • Time synchronization is accurate (network-wide deviation ≤ 1 second).
  • Alarm linkage, motion detection, and intelligent analysis work as designed.
  • Remote access (client/mobile) available.
  • The splicing screen is installed on the wall and the plan patrol is normal.

Stability

  • Run continuously for 72 hours without any abnormality.
  • The device online rate is 100%.
  • No flickering, disconnection, or missing video.
  • The hard disk status is normal and there are no bad sector alarms.

Completion information list

  1. As-built drawings: site layout diagram, system topology diagram, network structure diagram, cabinet layout diagram.
  2. Point ledger: number, location, model, IP, coverage area, installation date.
  3. Device list: model, quantity, serial number, firmware version, warranty information.
  4. IP and port comparison table: IP ↔ MAC ↔ switch port ↔ location.
  5. Test records: network test, ground resistance test, image effect screenshots (including night vision).
  6. Configuration Document: Key configuration instructions for NVR/switch/camera.
  7. Account list: Description of each system administrator account and permissions.
  8. Operation manual: daily operations, playback, export, common troubleshooting.
  9. Training records: training content, participants, sign-in sheet.
  10. Acceptance report: signed and confirmed by both parties.

Training Points

  • Administrator: configuration, account, storage, backup, upgrade.
  • Operator: preview, playback, export, alarm handling.
  • Provide written operation manuals and quick operation cards.
  • Clear the channels for reporting repairs and the response time limit.

Items that are easy to miss

  • The administrator account and password have not been transferred (or the password is still the default value).
  • There is no IP and port comparison table, making it difficult to troubleshoot later.
  • No ground resistance test records were made.
  • No screenshots of the night effect were retained, and there is no basis for subsequent disputes.
  • The warranty scope and response time limit are not specified.